with the new addition to my family (An SGI Onyx, Crimson, Indy, and Indigo2)
I realize they my room will no longer cut it. I need to move.
My first choice is Our storage room. It was an addition to our house and excluding the wall of the house all the walls are concrete and the room has the walls and ceiling insulated. The only problem is that there is a ruptured vapor barrier and the floor can get wet (not to the point of getting your feet wet but boxes go soggy over time).
Anyways, To power my systems I need to add another breaker panel since the current one has been framed in and drywall will have to be cut in order to cater for my addition. It also lacks enough blank spaces for the new breakers.
Attached is a rough layout of what I am planning.
Besides a new panel for both 120 and 220V service (Probably loooking at a 60 amp panel but it depends on what's installed in the two deskside systems so I'm assuming they are maxed systems) I also plan to install a second and personal hydro meter to see just how much current I am drawing. It is rated for 100A max throughput and accepts both 120 and 220 volts.
You can also see that the new panel is essentially on the other side of the wall.
Question 1:
Should I use conduit to go from the new panel, to the meter and then to the existing panel?
Quetion 2: Would it be wise to install a master disconnect between the existing panel and the new meter to isolate and lockout my addition if needed?
Question 3: I can get hold of a Pushmatic breaker panel as well as breakers. Should those be used or is it better to use toggle breakers?
BTW, my parents say I have to pay for all the supplies and they need to be in code or else they won't allow it.
I realize they my room will no longer cut it. I need to move.
My first choice is Our storage room. It was an addition to our house and excluding the wall of the house all the walls are concrete and the room has the walls and ceiling insulated. The only problem is that there is a ruptured vapor barrier and the floor can get wet (not to the point of getting your feet wet but boxes go soggy over time).
Anyways, To power my systems I need to add another breaker panel since the current one has been framed in and drywall will have to be cut in order to cater for my addition. It also lacks enough blank spaces for the new breakers.
Attached is a rough layout of what I am planning.
Besides a new panel for both 120 and 220V service (Probably loooking at a 60 amp panel but it depends on what's installed in the two deskside systems so I'm assuming they are maxed systems) I also plan to install a second and personal hydro meter to see just how much current I am drawing. It is rated for 100A max throughput and accepts both 120 and 220 volts.
You can also see that the new panel is essentially on the other side of the wall.
Question 1:
Should I use conduit to go from the new panel, to the meter and then to the existing panel?
Quetion 2: Would it be wise to install a master disconnect between the existing panel and the new meter to isolate and lockout my addition if needed?
Question 3: I can get hold of a Pushmatic breaker panel as well as breakers. Should those be used or is it better to use toggle breakers?
BTW, my parents say I have to pay for all the supplies and they need to be in code or else they won't allow it.
Comment